Mold opening and new product review (DFM → customer) twice feasibility (DFM design and development documents) (2 DAY)
Step 1:Mold Design: Drawing (2 DAY)
Step 2:Raw material procurement, preparation: die steel cutting, from rough to leather (2 DAY)
Step 3:Machining: punching and CNC notching (2 DAY)
Heat treatment: 6 pieces in the middle of the mold → cryogenic →1 to 2 DAY→ increase hardness (3 DAY)
Grinding: Large water grinding (2 DAY)
Wire cutting: copper wire slow wire (3 DAY)
CNC Fine Wash (2 DAY)
Step 4:T0 proofing and T1 proofing shall be carried out after the completion of assembly trial mold (2 DAY)
Total 20 days from new product opening review to mold completion
Quotation involves mold design, raw materials, machining (heat treatment, grinding, wire cutting, fine washing), working hours and other costs

Precision Punch
Quantity: 22 units


CNC Machining Center
Quantity: 2 units


Slow Wire Cutting
Quantity: 3 units



Fully Automatic 2D Image Measuring Instrument

High Temperature Experiment Box

RoHS Detection Spectrometer

Salt Spray Tester

Surface Roughness Tester

Height Master